Project details
- Project Size: 3 Level Parking Garage Structure
- Project Location: Rockville, Maryland
- Budgeted Construction Costs: $3,000,000
- Actual Construction Costs: $3,000,000
- Completion Date: 2007
- Client: Information Available Upon Request
- Owner: Information Available Upon Request
Rockville Doubletree Hotel
Rockville Doubletree Hotel: Deteriorated Reinforced Concrete Parking Deck Slabs Restoration
Biller Reinhart Engineering Group, Inc. prepared design drawings and specifications and bid documents for the restoration and partial removal and replacement of deteriorated reinforced concrete parking deck slabs for the 3-level parking structure. BillerReinhart assisted the client and owner during the bidding phase of the project to select a contractor to perform the restoration work. BillerReinhart also performed construction administration services including the following: conducting site visits during the restoration work to observe construction progress, submitting reports documenting the work, and reviewing contractor pay requests.